Question 1 of 40The ITIL Value System

For every report it produces, a team asks who uses it and which outcome it supports. It stops producing the reports nobody uses. Which guiding principle is the team applying?

AStart where you are
BOptimise and automate
CProgress iteratively with feedback
D ✓Focus on value
Explanation: Focus on value means everything the organisation does should link, directly or indirectly, to value for stakeholders. Reports that support no outcome add no value.
Question 2 of 40The ITIL Value System

Identify the missing word(s) in the following sentence. In the continual improvement model, the step '[ ? ]' provides the direction for an improvement and should be aligned with the organisation's goals.

A ✓What is the vision?
BTake action
CWhere are we now?
DHow do we keep the momentum going?
Explanation: What is the vision? is the first step. It sets the direction for the improvement and must link to the organisation's goals and objectives.
Question 3 of 40The ITIL Value System

Which of the following is NOT a characteristic of the ITIL value chain activities?

AThey are iterative and non-linear
BValue streams combine them in different ways
C ✓They must always be performed in a fixed sequence
DThey cover everything from discovering needs to supporting consumers
Explanation: The activities are iterative and non-linear, and value streams combine them as needed. They are not performed in a fixed order.
Question 4 of 40The ITIL Value System

Which of the following is NOT an appropriate use of continual improvement?

A ✓Improving only after a major failure has occurred
BLinking an improvement to a stated vision
CChecking whether a planned improvement achieved its target
DKeeping up momentum once an improvement is delivered
Explanation: Continual improvement is a recurring activity, not something reserved for after a major failure. Improvements link to a vision, are checked against targets and are sustained.
Question 5 of 40The ITIL Value System

A project plan for a new storage service covers backup, staff training, the supplier contract and how costs will be recharged, all at the same time rather than one by one. Which guiding principle does this BEST reflect?

AKeep it simple and practical
BStart where you are
C ✓Think and work holistically
DCollaborate and promote visibility
Explanation: Think and work holistically means recognising that no service, practice or component stands alone. Results are delivered through the interaction of all the parts.
Question 6 of 40The ITIL Value System

Which TWO statements about the ITIL value chain are correct? 1. It consists of eight activities 2. Its activities must always be performed in strict order from Discover to Support 3. Value streams select the activities needed for a particular outcome 4. It applies only to IT departments

A1 and 2
B ✓1 and 3
C2 and 4
D3 and 4
Explanation: The value chain has eight activities, and a value stream is a specific path through them. The activities are not a fixed sequence, and the model is not limited to IT departments.
Question 7 of 40The ITIL Value System

Which of the following is NOT an example of the guiding principle 'Collaborate and promote visibility'?

A ✓Keeping a team's work hidden until it is finished
BSharing progress with stakeholders regularly
CWorking across team boundaries
DMaking work visible on a shared board
Explanation: This principle encourages working together and making work visible. Hiding work until it is finished is the opposite.
Question 8 of 40The ITIL Value System

Which of the following would NOT be an appropriate use of the guiding principle 'Start where you are'?

AObserving the current situation directly
BReusing existing services and processes that already work
CMeasuring what exists before deciding what to change
D ✓Discarding all existing services and processes before assessing them
Explanation: Start where you are means assessing what exists and building on what already works. Discarding everything before assessing it contradicts the principle.
Question 9 of 40The ITIL Value System

An organisation wants detailed guidance on applying Incident Management, including its purpose, key roles and metrics. Where should it look?

AThe ITIL guiding principles
B ✓The ITIL practice guide for that practice
CThe continual improvement model
DThe four dimensions of product and service management
Explanation: An ITIL practice guide expands a single management practice with detailed guidance such as purpose, success factors, key metrics, processes and roles.
Question 10 of 40The ITIL Value System

Which TWO of the following are steps in the ITIL continual improvement model? 1. Take action 2. Appoint a steering committee 3. Where are we now? 4. Select a supplier

A1 and 2
B2 and 4
C ✓1 and 3
D3 and 4
Explanation: Take action and Where are we now? are steps in the model. The others are not steps of the continual improvement model.
Question 11 of 40The ITIL Value System

Before buying a tool to automate approvals, a team removes the approval steps that nobody uses and then automates the remaining ones. Which guiding principle does this BEST reflect?

AFocus on value
B ✓Optimise and automate
CStart where you are
DCollaborate and promote visibility
Explanation: Optimise and automate says to simplify and optimise first and then automate. Automating a flawed or bloated process only makes the problems faster.
Question 12 of 40The ITIL Value System

Identify the missing word(s) in the following sentence. The guiding principle '[ ? ]' states that working across boundaries produces better buy-in, more relevance and a greater likelihood of long-term success.

AStart where you are
BOptimise and automate
C ✓Collaborate and promote visibility
DFocus on value
Explanation: Collaborate and promote visibility encourages working together across teams and with stakeholders, and making work visible, so that results are more relevant and more likely to last.
Question 13 of 40The ITIL Value System

Identify the missing word(s) in the following sentence. ITIL management practices are organised into two groups: general management practices and [ ? ] management practices.

Atechnical
Bservice
Cinfrastructure
D ✓product and service
Explanation: ITIL (Version 5) groups its 34 management practices into general management practices and product and service management practices. The separate technical group no longer exists.
Question 14 of 40The ITIL Value System

Which TWO statements about ITIL practice guides are correct? 1. They expand a practice with detail such as its purpose, success factors, metrics, processes and roles 2. They replace the ITIL guiding principles 3. They help an organisation apply a practice within its own value streams 4. They must be followed step by step without adapting them

A ✓1 and 3
B1 and 2
C2 and 4
D3 and 4
Explanation: Practice guides give detailed guidance on a practice and help an organisation fit it into its own value streams. They do not replace the guiding principles, and ITIL expects organisations to adopt and adapt guidance.
Question 15 of 40The ITIL Value System

A development team writes code for a new customer portal, integrates the components and runs its test suite. The portal is not yet available to customers. Which value chain activity does this BEST represent?

ATransition
B ✓Build
CDeliver
DAcquire
Explanation: Build develops and tests digital products, turning designs into working solutions. Transition would introduce the finished product into the live environment.
Question 16 of 40The ITIL Value System

Which TWO of the following are guiding principles of ITIL? 1. Think and work holistically 2. Maximise utilisation of every resource 3. Progress iteratively with feedback 4. Centralise all decisions

A ✓1 and 3
B1 and 2
C2 and 4
D3 and 4
Explanation: Think and work holistically and Progress iteratively with feedback are two of the seven guiding principles. Maximising utilisation and centralising decisions are not guiding principles.
Question 17 of 40Key ITIL terms and definitions

Which of the following would NOT normally be handled as a service request?

ARequesting access to a shared folder
B ✓Reporting that email has stopped working for the whole team
CRequesting a replacement mouse
DRequesting approved software to be installed
Explanation: A service request is a request for a routine, agreed service action. Email that has stopped working is an unplanned interruption, which is an incident.
Question 18 of 40Key ITIL terms and definitions

Which TWO of the following statements are correct? 1. An incident is an unplanned interruption to a service or reduction in its quality 2. A problem is an unplanned interruption to a service 3. A problem is a cause, or potential cause, of one or more incidents 4. A known error is a resolved incident

A1 and 2
B2 and 4
C ✓1 and 3
D3 and 4
Explanation: An incident is an unplanned interruption or reduction in quality. A problem is a cause or potential cause of incidents. A known error is a problem that has been analysed but not resolved.
Question 19 of 40Key ITIL terms and definitions

Which TWO of the following are components of a service offering? 1. Goods 2. Incidents 3. Access to resources 4. Known errors

A1 and 2
B2 and 4
C ✓1 and 3
D3 and 4
Explanation: A service offering is a description of one or more services, and it includes goods, access to resources and service actions. Incidents and known errors are not components of an offering.
Question 20 of 40Key ITIL terms and definitions

Which of the following is NOT an example of an output?

AA new release of an application
BA completed incident record
CA configured server
D ✓Payroll staff finish the payroll run two days faster than before
Explanation: Finishing payroll faster is a result for the stakeholder, so it is an outcome. A release, a record and a configured server are deliverables of activities, so they are outputs.
Question 21 of 40Key ITIL terms and definitions

Identify the missing word(s) in the following sentence. An [ ? ] is a result for a stakeholder that is enabled by one or more outputs.

A ✓outcome
Boutput
Cutility
Dincident
Explanation: An outcome is a result for a stakeholder enabled by one or more outputs. An output is a tangible or intangible deliverable of an activity.
Question 22 of 40Key ITIL terms and definitions

Identify the missing word(s) in the following sentence. [ ? ] is the functionality offered by a product or service to meet a particular need.

A ✓Utility
BWarranty
CRisk
DCost
Explanation: Utility is the functionality offered, or 'fit for purpose'. Warranty is the assurance that the product or service will meet agreed requirements, or 'fit for use'.
Question 23 of 40Key ITIL terms and definitions

Identify the missing word(s) in the following sentence. A [ ? ] is a person or organisation that has an interest or involvement in an organisation, product or service.

Asupplier
Bsponsor
C ✓stakeholder
Doutput
Explanation: A stakeholder is a person or organisation with an interest or involvement in an organisation, product, service or practice. Sponsors and suppliers are particular kinds of stakeholder.
Question 24 of 40Key ITIL terms and definitions

A company outsources its payroll to a specialist firm that runs the payroll platform on its behalf. Which role does the specialist firm play?

AService consumer
BSponsor
CUser
D ✓Service provider
Explanation: A service provider is an organisation that provides services to consumers. The company that uses the payroll service is the service consumer.
Question 25 of 40Key ITIL terms and definitions

In a large organisation, one manager approves the budget for the consumption of a service. Which role does this manager play?

AUser
BService provider
C ✓Sponsor
DSupplier
Explanation: A sponsor is a role that authorises budget for service consumption. A customer defines the requirements and a user uses the service.
Question 26 of 40Key ITIL terms and definitions

Identify the missing word(s) in the following sentence. An [ ? ] is a change of state that has significance for the management of a service or other configuration item.

Aincident
B ✓event
Cproblem
Doutcome
Explanation: An event is any change of state that has significance for the management of a service or configuration item. An event may or may not lead to an incident.
Question 27 of 40Key ITIL terms and definitions

Which TWO statements about cost and risk in the context of a service are correct? 1. A service can remove costs from the consumer 2. A service can never introduce new costs 3. A service can remove risks from the consumer 4. Risk refers only to a loss that has already happened

A1 and 2
B2 and 4
C3 and 4
D ✓1 and 3
Explanation: Services can remove costs and risks from the consumer, and they can also introduce new ones. Risk is about possible future events, not only losses that have already occurred.
Question 28 of 40Key ITIL terms and definitions

Which statement BEST describes the difference between a customer and a user?

AA customer uses the service; a user pays for it
BA customer is always external; a user is always internal
CA customer supplies the service; a user receives it
D ✓A customer defines requirements and takes responsibility for outcomes; a user uses the service
Explanation: Customers define the requirements for a service and take responsibility for the outcomes of consumption. Users are the people who use the service.
Question 29 of 40ITIL Product and Service Lifecycle

Which of the following is NOT an activity of the ITIL value chain?

ADiscover
BTransition
C ✓Audit
DDeliver
Explanation: Discover, Transition and Deliver are value chain activities. Audit is not one of the eight.
Question 30 of 40ITIL Product and Service Lifecycle

Identify the missing word(s) in the following sentence. The value chain activity '[ ? ]' keeps live products and services reliable, secure and performing.

AAcquire
B ✓Operate
CDiscover
DDesign
Explanation: Operate keeps live products and services reliable, secure and performing. Acquire obtains resources, Discover clarifies needs and Design defines how the product or service will work.
Question 31 of 40ITIL Product and Service Lifecycle

A team's pipeline builds and tests every change and keeps each build in a releasable state, but a person decides when to release it to production. Which practice does this describe?

A ✓Continuous delivery
BContinuous deployment
CContinuous integration
DObservability
Explanation: Continuous delivery keeps software in a state where it can be released at any time, with the release itself a deliberate decision. Continuous deployment releases automatically.
Question 32 of 40ITIL Product and Service Lifecycle

Which TWO of the following are value chain activities? 1. Transition 2. Audit 3. Operate 4. Budget

A1 and 2
B ✓1 and 3
C2 and 4
D3 and 4
Explanation: Transition and Operate are among the eight value chain activities. Audit and Budget are not.
Question 33 of 40The ITIL Four Dimensions

A company redesigns job roles in its service desk, changes the reporting lines and runs a training programme for the new team. Which dimension of product and service management is MOST relevant?

AInformation and technology
BPartners and suppliers
CValue streams and processes
D ✓Organisations and people
Explanation: Organisations and people covers structure, roles, culture, skills and competencies.
Question 34 of 40The ITIL Four Dimensions

Which TWO of the following are among the four dimensions of product and service management? 1. Partners and suppliers 2. Guiding principles 3. Value streams and processes 4. Governance

A1 and 2
B2 and 4
C ✓1 and 3
D3 and 4
Explanation: The four dimensions are Organisations and people, Information and technology, Partners and suppliers, and Value streams and processes. Guiding principles and governance are components of the value system.
Question 35 of 40The ITIL Four Dimensions

Which of the following would NOT be considered part of the 'Information and technology' dimension?

AKnowledge shared with stakeholders
BAutomation and monitoring tools
CInformation about the status of services
D ✓Staff skills and competencies
Explanation: Skills and competencies belong to Organisations and people. Information, knowledge and the technologies that handle them belong to Information and technology.
Question 36 of 40The ITIL Four Dimensions

Identify the missing word(s) in the following sentence. The four dimensions are Organisations and people, Information and technology, Partners and suppliers and [ ? ].

AGuiding principles
B ✓Value streams and processes
CContinual improvement
DGovernance
Explanation: Value streams and processes is the fourth dimension. The mnemonic is VOIP.
Question 37 of 40Value stream identification, mapping, and management

Which TWO statements about value streams are correct? 1. A value stream is a series of steps used to create and deliver products and services to a consumer 2. Every value stream uses all eight value chain activities 3. Value streams can be mapped to find waste and delays 4. A value stream is the same thing as a practice

A1 and 2
B2 and 4
C3 and 4
D ✓1 and 3
Explanation: A value stream is a series of steps, and mapping it reveals waste. Value streams select only the value chain activities they need, and they are not practices.
Question 38 of 40Value stream identification, mapping, and management

Value stream mapping shows that a request takes 12 hours from start to finish, but only 3 hours of that time is spent on real work. What proportion of the time is value-adding?

A75%
B ✓25%
C33%
D4%
Explanation: 3 hours of work in 12 hours elapsed is 25%. The remaining 75% is waiting, which is the main target for improvement.
Question 39 of 40ITIL and AI

Which of the following is NOT one of the capabilities in the ITIL AI capability model (the 6Cs)?

A ✓Compliance
BCreation
CCuration
DCommunication
Explanation: The six capabilities are Creation, Curation, Clarification, Cognition, Communication and Coordination. Compliance is not one of them.
Question 40 of 40ITIL and other frameworks

Which TWO statements about ITIL and DevOps are correct? 1. They can be used together 2. DevOps makes ITIL obsolete 3. DevOps practices such as continuous integration can support the value chain 4. ITIL forbids automation

A ✓1 and 3
B1 and 2
C2 and 4
D3 and 4
Explanation: The syllabus presents ITIL and DevOps as complementary. DevOps practices support the product and service lifecycle, and ITIL encourages appropriate automation.

Ready to test yourself under real conditions?